Demolition East Sussex

Taylor Wimpey

[minti_iconbox iconimg=”17295″ style=”4″ title=”Demolition” url=”http://matthewsgroup.co.uk/demolition/”][/minti_iconbox]
[minti_iconbox iconimg=”17298″ style=”4″ title=”Earthworks & Enabling Contracts” url=”http://matthewsgroup.co.uk/earthworks-and-landscaping/”][/minti_iconbox]
[minti_iconbox iconimg=”17301″ style=”4″ title=”Haulage” url=”http://matthewsgroup.co.uk/haulage/”][/minti_iconbox]
[minti_iconbox iconimg=”17299″ style=”4″ title=”Muck Away & Waste Disposal” url=”http://matthewsgroup.co.uk/muck-away-waste-disposal/”][/minti_iconbox]
[minti_iconbox iconimg=”17303″ style=”4″ title=”Plant Hire” url=”http://matthewsgroup.co.uk/plant-hire/”][/minti_iconbox]
[minti_iconbox iconimg=”17376″ style=”4″ title=”Soil Remediation & Validation” url=”http://matthewsgroup.co.uk/soil-remediation-sussex/”][/minti_iconbox]
[minti_headline size=”fontsize-m” weight=”fontweight-400″ lineheight=”lh-13″ transform=”transform-uppercase” margin=”10px 0 0 0″]Muck Away & Waste Disposal • Demolition • Earthworks & Enabling Contracts • Haulage • Plant Hire • Soil Remediation & Validation[/minti_headline][minti_headline size=”fontsize-l” weight=”fontweight-800″ margin=”0 0 10px 0″]Call us now on 01293 617014[/minti_headline]
[minti_headline type=”h3″ size=”fontsize-l” color=”#f36e32″ weight=”fontweight-600″ transform=”transform-uppercase” align=”align-left”]Client: Taylor Wimpey[/minti_headline][minti_headline type=”h3″ size=”fontsize-m” color=”#0b4855″ weight=”fontweight-600″ align=”align-left” margin=”0 0 10px 0″]Start Date: April 2007[/minti_headline]

Background

Matthews worked as principle contractor for Taylor Wimpey in the demolition of the former Chailey Heritage Hospital in East Sussex.

[minti_image img=”16949″]

The Works

The scope of works included the safe removal of asbestos, soft stripping, structural demolition and site clearance as well as the crushing of concrete for re-use across the development. Matthews also worked in close conjunction with ecologists and assisted them in the relocation of a large bat colony, which had made the site their home.

Work commenced in July 2006 and the first phase was completed by December 2006. The bats have now been safely relocated and Phase 2 of the project is due to start in the summer of 2007.

[minti_imagebox style=”2″]

Call us now on 01293 617014 to discuss a project

[minti_spacer height=”15″]

[minti_button link=”mailto:[email protected]” size=”large” target=”” lightbox=”false” color=”color-2″ icon=”fa-chevron-right” appear=”true”]Email Us Here[/minti_button]

[/minti_imagebox][minti_divider style=”2″ margin=”0 0 40px 0″][minti_imagebox]

Click below to view more Recent Projects

[minti_spacer height=”4″]

[minti_button link=”http://matthewsgroup.co.uk/case-studies/” size=”large” target=”” lightbox=”false” color=”color-3″ icon=”fa-chevron-right” appear=”true”]View Recent Projects[/minti_button]

[/minti_imagebox]

No Comments

Sorry, the comment form is closed at this time.