Demolition Battersea

Volkswagen Lookers, Battersea

[minti_iconbox iconimg=”17295″ style=”4″ title=”Demolition” url=”http://matthewsgroup.co.uk/demolition/”][/minti_iconbox]
[minti_iconbox iconimg=”17298″ style=”4″ title=”Earthworks & Enabling Contracts” url=”http://matthewsgroup.co.uk/earthworks-and-landscaping/”][/minti_iconbox]
[minti_iconbox iconimg=”17301″ style=”4″ title=”Haulage” url=”http://matthewsgroup.co.uk/haulage/”][/minti_iconbox]
[minti_iconbox iconimg=”17299″ style=”4″ title=”Muck Away & Waste Disposal” url=”http://matthewsgroup.co.uk/muck-away-waste-disposal/”][/minti_iconbox]
[minti_iconbox iconimg=”17303″ style=”4″ title=”Plant Hire” url=”http://matthewsgroup.co.uk/plant-hire/”][/minti_iconbox]
[minti_iconbox iconimg=”17376″ style=”4″ title=”Soil Remediation & Validation” url=”http://matthewsgroup.co.uk/soil-remediation-sussex/”][/minti_iconbox]
[minti_headline size=”fontsize-m” weight=”fontweight-400″ lineheight=”lh-13″ transform=”transform-uppercase” margin=”10px 0 0 0″]Muck Away & Waste Disposal • Demolition • Earthworks & Enabling Contracts • Haulage • Plant Hire • Soil Remediation & Validation[/minti_headline][minti_headline size=”fontsize-l” weight=”fontweight-800″ margin=”0 0 10px 0″]Call us now on 01293 617014[/minti_headline]
[minti_headline type=”h3″ size=”fontsize-l” color=”#f36e32″ weight=”fontweight-600″ transform=”transform-uppercase” align=”align-left”]Client: Linden Homes[/minti_headline][minti_headline type=”h3″ size=”fontsize-m” color=”#0b4855″ weight=”fontweight-600″ align=”align-left” margin=”0 0 10px 0″]Site: Volkswagen Lookers, Battersea
[/minti_headline][minti_spacer]

Project Overview

This project involved the demolition and site clearance of the 5,000m2 former Volkswagen Showroom and garages, bulk excavation and remediation.

[minti_image img=”17159″]

Project Considerations

The former Volkswagen showroom and associated garages were located in the heart of Battersea, where major regeneration has been underway for the past decade. The site was located close to the River Thames and next door to a private heliport.

One of the major hurdles MSL faced was that major regeneration of the area has been completed and there are now multiple multi-million pound properties, and residents who did not wish to have the potential noise and dust disturbance. Local residents were supplied with fortnightly newsletters explaining our process and also site contact details as well as MSL Head Office details.

Linden Homes were conscious of the fact that the residents were not happy about having any disruption for such a prolonged period of time. MSL came up with a methodology that took this in to consideration. We used specially commissioned noise dampened shears to cut the building in to manageable pieces prior to be taken off site. Ultra noise dampened breaker attachments were fitted to the excavators to break out the associated slabs and foundations as well as associated hard standings. We implemented a plan of work to minimise disruption to the client, selecting sensitive times of the day, following consultation with local residents, when noisy works would not happen. It was important to our client that we established and maintained a good relationship with residents as our works were relatively short in terms of programme compared to the rebuild.

Scaffold screens and demolition fans were erected where required to make sure that residents and businesses were protected and safe throughout our works.

[minti_imagebox style=”2″]

Call us now on 01293 617014 to discuss a project

[minti_spacer height=”15″]

[minti_button link=”mailto:[email protected]” size=”large” target=”” lightbox=”false” color=”color-2″ icon=”fa-chevron-right” appear=”true”]Email Us Here[/minti_button]

[/minti_imagebox]

[minti_image img=”17394″]

Scope of Works

  • Act as Principal Contractor
  • Establish site welfare
  • Carry out pre-demolition condition survey to the buildings being demolished and surrounding buildings
  • Carry out pre and post CCTV drainage surveys
  • Erection of scaffold
  • Demolition of buildings
  • Removal of non-licensed asbestos including personal monitoring and air testing
  • Purging, cleaning and removal of underground tanks
  • Excavation of 21,000m3 soil
  • Remediation of 15,000m3 contaminated soils
  • Disposal of 6000m3 of hazardous soils
  • Breaking out and removal of substructures
  • Land remediation including excavating of materials contaminated with asbestos and hydrocarbons to a depth of five metres
  • Crushing and stock piling of 6,000m3 of concrete to 6F2 specification
  • Installation of sheet piling to perimeter of site
  • Installation of piling mat
[minti_image img=”17396″][minti_divider style=”2″ margin=”0 0 40px 0″][minti_imagebox]

Click below to view more Recent Projects

[minti_spacer height=”4″]

[minti_button link=”http://matthewsgroup.co.uk/case-studies/” size=”large” target=”” lightbox=”false” color=”color-3″ icon=”fa-chevron-right” appear=”true”]View Recent Projects[/minti_button]

[/minti_imagebox]

No Comments

Post A Comment